The Police Chief has the authority to authorize emergency construction work that exceeds the Town's noise level limitations and hours of construction regulations. Requests are reviewed on a case by case basis and are typically for construction work that requires continuous work that cannot be delayed once it starts - such as concrete pours.

When permitting work, the contractor shall be required to notify all neighbors abutting the subject parcel along with those parcels directly across the street at least 72 hours in advance of the scheduled work. If the 72-hour advance notice is not possible due to the date of the issuance of the exemption, the contractor shall immediately upon approval of the exemption, notify surrounding residents of the scheduled work. Failure to notify surrounding residents may prevent future exemption approvals.

Below is a list of permits issued pursuant to the above:

  • September 10 - 52 Middlefield Rd. - 7: 00 a.m. - 7:00 p.m. - pool gunite
  • September 11 - 395 Selby Lane - 6:00 a.m. - 7:00 p.m. - concrete pour
  • September 12- 395 Selby Lane -6:00 a.m. - 7:00 p.m. - concrete pour
  • September 13 - 156 Stockbridge - 8:00 a.m. - 5:00 p.m. - concrete pour
  • September 13 - Middlefield Rd/ & Palmer/Ravenswood - 8:00 a.m. - 5:00 p.m. - Remove Thermal Striping
  • September 14 -   Middlefield Rd/ & Palmer/Ravenswood - 8:00 a.m. - 5:00 p.m. -  Microseal 
  • September 15 -  Middlefield Rd/ & Palmer/Ravenswood - 8:00 a.m. - 5:00 p.m. - Microseal
  • September 16 - 233 Park Lane - 7:00 a.m. - 6:00 p.m. - shotcrete
  • September 16 - 91 Ashfield Rd. - 8:00 a.m. - 7:00 p.m. - concrete pour
  • September 17 - 233 Park Lane - 7:00 a.m. - 6:00 p.m. - shotcrete
  • September 17 - 91 Ashfield Rd. - 8:00 a.m. - 7:00 p.m. - concrete pour
  • September 18 - 91 Ashfield Rd. - 8:00 a.m. - 7:00 p.m. - concrete pour
  • September 19 - 91 Ashfield Rd. - 8:00 a.m. - 7:00 p.m. - concrete pour
  • September 21 - Middlefield Rd/ & Palmer/Ravenswood - 8:00 a.m. - 5:00 p.m. - Microseal
  • September 22 - Middlefield Rd/ & Palmer/Ravenswood - 8:00 a.m. - 5:00 p.m. - Microseal
  • September 28 - Middlefield Rd/ & Palmer/Ravenswood - 8:00 a.m. - 5:00 p.m. - Microseal
  • September 29 - Middlefield Rd/ & Palmer/Ravenswood - 8:00 a.m. - 5:00 p.m. - Microseal 

Note to residents: PG&E Notice